DDK's Guide to the Estimation of IT Projects

As an Architect and the .NET Principal at Oakton NSW, I have to do my fair share of Estimates and Proposals. I am also often asked to review and revise other peoples estimates - to "Quality Stamp" them so to speak. There are some common things that I pick up on - hence the driver behind this blog post.

Summary Diagram of the DDK Estimation Technique:



Here are some of the important things you should consider when developing estimates:

1. Estimate from the bottom up rather than from the top down. The focus and detail of this approach helps you to substantiate your estimates to others and show you've used due diligence in arriving at your estimate. A detailed function point analysis (FPA) is ideal when trying to minimise risk as much as possible (especially for fixed cost projects).
2. There are 2 critical variables which can make a project take much longer than expected and estimated. If you have these components, you need to increase your estimate to more than you expect:
  a. The larger and more complex the project, the more likely it is to take longer than expected.
  b. The more new technologies or new techniques involved, the more likely it is to take longer than expected

3. Communicate with and update the client regularly – Don’t be afraid to re-estimate your tasks and let the client know if things will take longer or shorter than expected. The earlier they know, the earlier corrective action can be taken.

4. Larger projects are harder to estimate. Only estimate small components of a project if possible – don’t estimate all releases. Deliver and estimate in increments if the client/contracts allow.

5. Make sure you consider the following components in your Estimation Checklist before giving it to the client:
  a. End User Documentation
  b. System Documentation
    i. Rollback Plans
    ii. Non Functional Requirements (NFR)
    iii. Technical Design & Specifications
    iv. Functional Design & Specifications
    v. Establishing Metrics (e.g. what performance is expected on what servers and with what data load)
    vi. Test Plans
    vii. Test Scripts
  c. Testing
  d. Training and Change Management (you can't just give someone an application and expect them to start using it effectively!)
  e. User Acceptance Testing
  f. Integration Testing (esp when integrating with Legacy Systems)
  g. Deployment Activities and Productionizing Systems
    i. Especially with complex deployments. These deployment activities are typically ongoing rather than once off.
  h. Meetings Drag Factors such as regular Meetings and Discussions. Team leaders and architects need a drag factor SCRUM meetings and requirement gathering meetings.
    i. Triage Meetings
    ii. Code Reviews
    iii. Level 2 Reviews by Testers e.g. For one of our projects, it took an average of 45 minutes per TFS work item/ticket.
  i. Focus Groups
  j. Licenses
  k. Configuration
    i. Third Party Components
    ii. Firewall Configuration
    iii. Database Configuration
  l. Data Migration
  m. Handovers (Including Warranty Periods)
  n. You need to anticipate who is developing it.
    i. Offshore Models/Engagements – have to spend 2-3 times the effort in non-development activities such as coordination, “hand-holding” and quality assurance when your team is overseas. You also need to spend much more time on specification documents to avoid communication issues.
  o. Temper your Optimism by considering different scenarios
    i. Best Case
    ii. Worst Case
    iii. Likely Case Scenario
  p. If uncertainty on a project is High, add an uncertainty multiplier to your estimate
  q. Don’t estimate more than 8 hours per day.
  r. Budget time for Performance Testing
    i. Time for Load Tests

6. If possible, do a Proof of Concept (PoC) before providing the estimates (or just estimate the PoC) – especially when using new combinations of technologies.

7. Learn from Historical Data. Try to learn from similar projects and how the estimates compared with the actuals. Use your company portal to discover estimates and ask other people in your company for similar estimates that they did.

8. Sanity Check your estimates. i.e. Have your estimates peer-reviewed to help you ensure consistency and coverage in your estimates.

9. Cross-Check your estimates. If you can convince all stakeholders that the estimate is valid and establish buy-in to that estimate, you have the basis of a good estimate.

10. Don’t underestimate Non-Programming/Infrastructure activities.

11. Don’t change estimates if possible if they are based on a solid agreement or understanding. Instead, try and change the commercial arrangements surrounding the estimate. E.g. don’t change the estimates unless they are proven unreasonable – change the rate if possible.

12. All estimates are guesses – try and reduce the uncertainty – but you cannot remove uncertainty completely.

13. Try to make your estimates from a fully informed standpoint - the same as a General shouldn't make strategic decisions in the fog of war. Request and Review as many materials (including scribbled diagrams and requirements documents) as time allows. The more you discuss your understanding of the project and talk to the end users, the more likely you are to make an informed estimate. Again, this allows you to back up your estimates to all stakeholders. If there are factors in the project that are particularly unclear or uncertain, add an "uncertainty" multiplier on the item. Encourage the client to help you clear up this uncertainty if possible.

14. Use the right tools. Microsoft Project is a good start. Learn how to use it properly - plus it can then create and update developer work items for you in Microsoft Team Foundation Server (TFS)  when you are ready to start work.

15. Don't forget that external dependencies (e.g. a 3rd party is creating web services for you, waiting on documentation) will slow the project down. Ideally start the project when work you depend on is complete - otherwise you'll need to factor downtime into your budget, estimates (an expected "downtime" item) and estimate assumptions.

Any thoughts or comments on this guide and checklist are welcome - I will update the list based on feedback.

DDK

26 comments:

  1. I actually enjoyed reading through this posting.Many thanks.



    Function Point Estimation Training

    ReplyDelete

  2. I actually enjoyed reading through this posting.Many thanks.



    Function Point Estimation Training in Chennai

    ReplyDelete

  3. My cousin recommended this blog and she was totally right keep up the fantastic work!
    Function Point Estimation Training

    ReplyDelete
  4. Really awesome blog. Thanks for sharing this informative blog. Suppose if anyone want to learn Software Testing Training in Chennai at a reputed training institutes. If you are looking for best Software Testing Training Institutes in Chennai reach FITA located at Chennai, India. Rated as No.1 placement and training center in Chennai.

    ReplyDelete

  5. Really awesome blog. Your blog is really useful for me. Thanks for sharing this informative blog. Keep update your blog.


    ISTQB Training Institute in Chennai

    ReplyDelete
  6. It's an impressive article. Thank you for sharing. Keep updating this kind of useful information.

    Manual Testing Training in Chennai | Manual Testing courses in Chennai

    ReplyDelete
  7. I am really enjoying reading your well written articles.
    It looks like you spend a lot of effort and time on your blog.
    I have bookmarked it and I am looking forward to reading new articles. Keep up the good work..
    Java Training in Bangalore
    Java Training Classes in Bangalore
    Java Training Courses in Bangalore
    Best Institute For Java Training In Bangalore

    ReplyDelete
  8. Link building, simply put, is the process of getting other websites to link back to your website. ... Building links is one of the many tactics used in search engine optimization (SEO) because links are a signal to Google that your site is a quality resource worthy of citation. share more
    Ai & Artificial Intelligence Course in Chennai
    PHP Training in Chennai
    Ethical Hacking Course in Chennai Blue Prism Training in Chennai
    UiPath Training in Chennai

    ReplyDelete
  9. Thanks for sharing an informative blog keep rocking bring more details.I like the helpful info you provide in your articles. I’ll bookmark your weblog and check again here regularly.
    Java training in Chennai

    Java Online training in Chennai

    Java Course in Chennai

    Best JAVA Training Institutes in Chennai

    Java training in Bangalore

    Java training in Hyderabad

    Java Training in Coimbatore

    Java Training

    Java Online Training

    ReplyDelete
  10. This blog is the general information for the feature. You got a good work for these blog.We have a developing our creative content of this mind.Thank you for this blog. This for very interesting and useful.
    DevOps Training in Chennai

    DevOps Online Training in Chennai

    DevOps Training in Bangalore

    DevOps Training in Hyderabad

    DevOps Training in Coimbatore

    DevOps Training

    DevOps Online Training

    ReplyDelete
  11. Positive site, where did u come up with the information on this posting?I have read a few of the articles on your website now, and I really like your style. Thanks a million and please keep up the effective work.
    Data Science Training In Chennai

    Data Science Online Training In Chennai

    Data Science Training In Bangalore

    Data Science Training In Hyderabad

    Data Science Training In Coimbatore

    Data Science Training

    Data Science Online Training

    ReplyDelete
  12. Nice article i was really impressed by seeing this article, it was very interesting and it is very useful for me.This is incredible,I feel really happy to have seen your webpage.I gained many unknown information, the way you have clearly explained is really fantastic.keep posting such useful information.

    IELTS Coaching in chennai

    German Classes in Chennai

    GRE Coaching Classes in Chennai

    TOEFL Coaching in Chennai

    spoken english classes in chennai | Communication training

    ReplyDelete
  13. Azure job support involves providing assistance to professionals working with Microsoft Azure, addressing challenges, and ensuring the successful implementation of Azure services. Here's an outline for Azure job suppor

    ReplyDelete
  14. This is a practical guide to IT estimation! Accurate estimation is one of the most challenging aspects of software development and IT project management. Your guide covers the key principles—understanding requirements, breaking down tasks, considering risks, and using historical data. For project managers and technical leads, these skills are essential for successful project delivery. As AI tools begin to assist with estimation and project planning, understanding traditional methods remains important. I've been exploring Gen AI and Agentic AI training near me in Electronic City to understand how AI is transforming project management and estimation processes. Thanks for sharing this practical guide!

    ReplyDelete